13 January 2026
NTA Activities
- Basement Excavation Work - 60% Completed
- PCC - 10% Completed
- Footing- 10% Completed
- Column up to basement 1 LVL - 10% Completed
- Next Milestone - Slab & Beam (B1 LVL), Stitching Slab
Basement Excavation Work: 60% completed
PCC: 10% completed
Footing: 10% completed
Columns up to Basement 1 Level: 10% completed
Slab & beam work at B1 level and stitching slab: Yet to start